RCE -
A5 Crossing Milton Keynes

 
 

Project details

  • Client: Roger Civil Engineering Limited

  • Location: A5 Crossing Milton Keynes

  • Duration: 2 weeks, completed ahead of schedule

  • Utilised: JT40

  • Ground Conditions: Clay

  • Installation: 225mm and 125mm twin Electric circuit

  • Completed all butt-welding and internal de-beading of the pipe